Aztec Red pavers make a strong statement in Aotea Square John Fillmore Contracting works on the project included the pavers, along with structural and precast concrete

Civil engineering contracting company John Fillmore Contracting was architecture, daylighting, fence, handrail, roof, steel, structure, walkway, gray
Civil engineering contracting company John Fillmore Contracting was responsible for the construction of the steel reinforced concrete slab and paving in the renovated Aotea Square.

In any large piazza, the paving underfoot is a defining feature, and Aotea Square is no exception. With its wide steps leading down from Queen St, the paved area at Aotea Square forms a natural amphitheatre, enhancing the civic amenity.

John Fillmore Contracting (JFC) works included all the structural concrete, from the car park roof deck up; all the above-ground structures, including steps, walls and terraces; and more than 7500m² of paving.

JFC was faced with many challenges during construction. Working around demolition and reconstruction of the new car park roof meant the staging of works put pressure on the programme from the outset. Having to negotiate the wet winter months also meant JFC worked around the clock to bring the project in on time.


Civil engineering contracting company John Fillmore Contracting was building, city, cloud, landmark, sky, town, track, transport, tree, vehicle, gray
Civil engineering contracting company John Fillmore Contracting was responsible for the construction of the steel reinforced concrete slab and paving in the renovated Aotea Square.

The main features of the project included the construction of the Queen St steps, the main entry steps leading up to the Aotea Centre, and the walls that define the southern border of the square.

All the precast concrete elements used in the construction were designed specifically for the project. The Queen St steps and terraces are a beige Aotea All In mix; the main entry stairs are a honed misty grey pebble mix; and the south walls and feature walls have a honed black finish.

Another feature was the use of Aztec Red granite paving, which covered more than 6000m².

Civil engineering contracting company John Fillmore Contracting was building, city, cloud, landmark, sky, town, track, transport, tree, vehicle, gray
Civil engineering contracting company John Fillmore Contracting was responsible for the construction of the steel reinforced concrete slab and paving in the renovated Aotea Square.

JFC is a privately owned infrastructure company involved in all aspects of civil construction. The firm has worked on many projects in partnership with the Auckland Council over the past 40 years, with the most recent projects being the St Patricks Square, Vulcan Lane, Swanson Lane and K Rd projects. The company has been contracted for the Fort St, Elliott and Darby St shared space projects.

For more information, contact John Fillmore Contracting, PO Box 43243, Mangere 2153, phone (09) 256 2544, fax (09) 275 6146. Or visit the website: www.jfcltd.co.nz.

Story by: Trendsideas